Question: Question 15 (5 points) As the production planner for Make it Simple Manufacturing company, you have been given a bill of material for a bracket

Question 15 (5 points)

As the production planner for Make it Simple Manufacturing company, you have been given a bill of material for a bracket that is made up of a base, 4 springs, and 2 clamps. The base is assembled from one clamp and 3 housings. Each housing has 3 bearings and one shaft. There is no inventory on hand.

Design a product structure noting the quantities of each item and show the low-level coding. (2 marks)

Determine the gross quantities needed for each item if you are to assemble 100 brackets. (1mark)

Compute the net quantities needed if there are 50 of the base and 200 of the clamp in stock. (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!