Question: QUESTION 15 Table 1: Notional Product Development Life Cycle Consider the Product Development Life Cycle in Table 1 above, as well as sound project planning

QUESTION 15 Table 1: Notional Product Development Life Cycle Consider the Product Development Life Cycle in Table 1 above, as well as sound project planning practices. Which of the following deliverables is NOT essential to proceed into Concept Validation? a. A product acceptance plan. b. Well defined requirements. c. A Project Charter. d. A detailed cost estimate and schedule for concept validation