Question: Question 16 (1 point) 3 A project is 50% completed. The budget for the project is $80,000. Thus far $62,000 has been spent. The customer

Question 16 (1 point) 3 A project is 50% completed. The budget for the project is $80,000. Thus far $62,000 has been spent. The customer is very concerned about project cost performance and is pressuring the Project Manager to improve performance. What is the Earned Value of the project thus far? 6 1 $ 31,000 9 $ 62,000 12 $ 72.000 $ 40,000 ) ENG 8:28 AM 2/13/2021 23