Question: Question 19 (1 point) A project is 50% completed. The budget for the project is $80,000. Thus far $62,000 has been spent. The customer is

Question 19 (1 point) A project is 50% completed.

Question 19 (1 point) A project is 50% completed. The budget for the project is $80,000. Thus far $62,000 has been spent. The customer is very concerned about project cost performance and is pressuring the Project Manager to improve performance. What is the Earned Value of the project thus far? $ 62,000 $ 72.000 O $ 31,000 $ 40.000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!