Question: Question 16 1 pts A project Manager is involved in monitoring of the project and the performance date reveals the following. A task should be

Question 16 1 pts A project Manager is involved
Question 16 1 pts A project Manager is involved in monitoring of the project and the performance date reveals the following. A task should be 1/4th complete. The budget of the task was $5500. He is trying to figure out the Planned value and having problems. You are a Subject Matter Expert and calculate the planned Value to be $1375 $ 2000 1500 1000 1 pts Ouestion 17