Question: Question 16 10 points A company is considering a project that has an up-front cost paid today at 10 The project will generate positive cash
Question 16 10 points A company is considering a project that has an up-front cost paid today at 10 The project will generate positive cash flows of 52,058 a year at the end of each for the next 5 years. The project's NPV is $33,237 and the company's return on the project is 98 percent What is the projects payburt