Question: Question 16 5 points When you collect the eared value data for your project, you get the following data: PV = $1,500,000. EV = $1.200.000,

Question 16 5 points When you collect the eared
Question 16 5 points When you collect the eared value data for your project, you get the following data: PV = $1,500,000. EV = $1.200.000, AC= $1,000,000. You expect the factors for cost variance to continue in the same way in future. The value of the remaining work is $1,000,000. What is the CPI