Question: QUESTION 16 A project manager reports the following data on status of a WP within his project which started on schedule, ED-20 weeks AD- 35

QUESTION 16 A project manager reports the
QUESTION 16 A project manager reports the following data on status of a WP within his project which started on schedule, ED-20 weeks AD- 35 weeks PD-25 week Using EDM the duration status of the WP is: Underestimated and behind schedule Overestimated and ahead of schedule Underestimated but ahead of schedule None of the above