Question: Question 16 - Every MRP record includes the following planning factors that are chosen by managers utilizing the MRP system except: Lot size is the
Question 16 - Every MRP record includes the following planning factors that are chosen by managers utilizing the MRP system except:
| Lot size is the quantity of a part to be produced or ordered when additional inventory is required. | |
| Lead time is the time between when an order is placed and when it is expected to arrive or be finished. | |
| Safety stock is excess inventory that a company holds to guard against uncertainty in demand, lead time, and supply. | |
| Order size is not specified since the user must verify with the supplier |
Step by Step Solution
There are 3 Steps involved in it