Question: Question 16 Often, the actual value- added work time in a task with in a process is a relatively small amount of the task cycle
Question 16 Often, the actual value- added work time in a task with in a process is a
relatively small amount of the task cycle time . What is the significance of this situation?
| re-balance the workload | |
| indicates that delays and non- value steps may be eliminated or reduces | |
| the potential to use automation to reduce cycle times | |
| level the workload |
Question 17 Kaizen teams are generally comprised of workers from all areas involved in
the process and can implement changes on the spot.
| True | |
| False |
Question 18 A kaizen team has found that defects have occurred because of a machine not working properly. What should team do in order to correct the defect situation.
| improve machine maintenance | |
| inspect the possibility of improving change over time | |
| apply mistake proofing | |
| collect utilization data on the machine |
Question 19The long term most powerful way to eliminate errors in a process is to identify
them and design the process so that they are eliminated from occurring.
| True | |
| False |
Question 20 When a kaizen team is brainstorming for improvement ideas of solutions to
a problem under study, only criticism of ideas that are not mainstream are not allowed.
| True | |
| False |