Question: Question 17 (1 point) 9 Listen Use the PERT Weighted average to estimate the duration of a task, in days, based on the following estimates:

 Question 17 (1 point) 9 Listen Use the PERT Weighted average

Question 17 (1 point) 9 Listen Use the PERT Weighted average to estimate the duration of a task, in days, based on the following estimates: 5 = Optimistic Time in Days, 23 - Most Likely Time in Days, 60 - Pessimistic Time in Days Provide your answer in whole numbers only, no decimals. Your