Question: Question 17 (1 point) 9 Listen Use the PERT Weighted average to estimate the duration of a task, in days, based on the following estimates:
Question 17 (1 point) 9 Listen Use the PERT Weighted average to estimate the duration of a task, in days, based on the following estimates: 5 = Optimistic Time in Days, 23 - Most Likely Time in Days, 60 - Pessimistic Time in Days Provide your answer in whole numbers only, no decimals. Your
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
