Question: Question 1[7 marks] Given the information in table below and using the same approach we used in class and in the book: Activity Predecessor Duration

 Question 1[7 marks] Given the information in table below and using

Question 1[7 marks] Given the information in table below and using the same approach we used in class and in the book: Activity Predecessor Duration (days) ES EF LS LF Slack None None 4 4 B, C D, E G, H a. Construct (i.e. draw) the network diagram b. Using the given table find each activity's ES, EF, LS, and LF (use the table) c. Calculate the slack for each activity (use the table) d. Find the critical path? (from the network in a) e. How long will the project take (i.e. the project duration)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!