Question: Question 17 Week 1 Week 2 Week 3 Week 4 Planned Actual CPI Value Cost 2200 2100 2900 3050 4650 4600 5400 5800 0.99 0.93)

Question 17 Week 1 Week 2 Week 3 Week 4 Planned
Question 17 Week 1 Week 2 Week 3 Week 4 Planned Actual CPI Value Cost 2200 2100 2900 3050 4650 4600 5400 5800 0.99 0.93) 0.85 0.951 Use the information in the table to determine the Schedule performance Index for Week 1 Your answer: 1.020 O 0.978 0.841 0 0.945 Clear