Question: Week 1 Week 2 Week 3 Week 4 Planned Actual CPI Value Cost 2200 2100 2900 3050 4650 4600 5400 5800 0.99 0.931 0.85 0.95

Week 1 Week 2 Week 3 Week 4 Planned Actual CPI Value Cost 2200 2100 2900 3050 4650 4600 5400 5800 0.99 0.931 0.85 0.95 Use the information in the table to determine the Schedule performance Index for Week 3 Your answer: 0.945 O 1.020 O 0.978 O 0.841