Question: Question 18 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time

Question 18 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time Time Time A 2 8 14 8 B 8 8 8 C A 6 9 18 D B 5 11 17 24 What is the minimum expected completion time for the project (please round off to two decimal digits)? Your