Question: Question 18 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time

Question 18 (1 point) The following represents a

Question 18 (1 point) The following represents a project with four activities. All times are in weeks. Most Immediate Optimistic Likely Pessimistic Activity Predecessor Time Time Time 2 18 14 11 17 What is the minimum expected completion time for the project (please round off to two decimal digits)? Your Answer: Your