Question: Question 18 (2 points) A project has a $1.5 million dollar plant purchase today. The project will run for three years from today, after which

Question 18 (2 points) A project has a $1.5 million dollar plant purchase today. The project will run for three years from today, after which the plant will be sold for $0 and have no tax consequences. The relevant discount rate is 6%. Please indicate the CCA expense schedule for the next three years, with a CCA rate of 40%. Furthermore, if the tax rate is 35%, what is the present value of the CCA tax shields