Question: QUESTION 19 A project is accepted if its IRR is OA less than or equal to the hurdle (or required) rate (i.e. 'r') OB. greater
QUESTION 19 A project is accepted if its IRR is OA less than or equal to the hurdle (or required) rate (i.e. 'r') OB. greater than the Net Present Value OC. equal to the Net Present Value OD. greater than the hurdle (or required) rate (i.e. 'r') QUESTION 20