Question: Question 2 0 0 . 2 5 p t s When using network diagrams for project management, the sequence of activities that has no slack
Question
When using network diagrams for project management, the sequence of activities that has no slack time is called the
A Critical Path
B Fast Lane
C Priority Trail
D Critical Sequence
E Acute Line