Question: Question 2 0 1 pts A work breakdown structure ( WBS ) defines the project component activities with unique identifying numbers linked directly to cost
Question
pts
A work breakdown structure WBS defines the project component activities with unique identifying numbers linked directly to cost codes, specific crews, materials, and equipment. Thus, WBStielps to monitor progress in terms of:
All of these
None of these
Time
Labor
Materials and Equipment