Question: Question 2 0 4 p t s . When making the final payment to a subcontractor, the construction manager should require the subcontractor to give

Question 20
4pts.
When making the final payment to a subcontractor, the construction manager should require the subcontractor to give which type of waiver of lien?
Final (Full) Conditional Waiver
Partial Conditional Waiver
Partial Unconditional Waiver
Final (Full) Unconditional Waiver