Question: QUESTION 2 0 Table of Crashing Decision table [ [ , TIME ( WEEKS ) , COST ( $ ) ] , [ ACTIVITY

QUESTION 20
Table of Crashing Decision
\table[[,TIME (WEEKS),COST ($)],[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],NORMAL,CRASH,NORMAL,CRASH],[A,---,3,2,3,000,3,300],[B,---,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]]
Since no indirect cost nor penaly cost information is offered, please consider the schedule and crash cost issues only,
Using Table of Crashing Decision, if the project's normal earliest completion time is to be reduced by two weeks, what is the minimum additional cost that will be incurred in achieving this two-week reduction?
less than or equal to $1,000
greater than $1,000 but less than or equal to $1,500
greater than $1,500 but less than or equal to $2,000
greater than $2,000
 QUESTION 20 Table of Crashing Decision \table[[,TIME (WEEKS),COST ($)],[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],NORMAL,CRASH,NORMAL,CRASH],[A,---,3,2,3,000,3,300],[B,---,6,4,8,000,9,000],[C,A,1,1,4,000,4,000],[,,,,,],[D,A,5,4,3,500,4,000],[E,B,4,3,4,750,5,500],[F,C,2,2,2,000,2,000],[,,,,,],[G,D,1,1,4,000,4,000],[H,D,F,3,2,3,500,3,750],[I,E,G,3,2,3,000,4,250],[J,E,2,1,5,000,7,000]] Since no

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!