Question: The following table shows the activities for a project. TIME ( WEEKS ) COST ( $ ) ACTIVITY IMMEDIATE PREDECESSOR ( S ) NORMAL CRASH
The following table shows the activities for a project.
TIME WEEKS COST $
ACTIVITY IMMEDIATE
PREDECESSORS
NORMAL CRASH NORMAL CRASH AVAILABL
E WEEKS
OF
CRASHING
CRASHIN
G COST
WEEK
A Start
B Start
C A
D A
E B
F C
G D
H DF
I EG
J E
Finish H I, J
a Draw the network diagram.
b What is the critical path for the project using the normal time?
c Complete the table by filling the missing information.
d How many weeks of crashing are available for activity E
e Which activity should be crashed first?
pts A professor records the number of complaints from his students each semester
throughout a semester period. The sample size for each sample is students, what are
sigma control limits for this class? Construct a control chart and interpret the data.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock