Question: The following table shows the activities for a project. TIME ( WEEKS ) COST ( $ ) ACTIVITY IMMEDIATE PREDECESSOR ( S ) NORMAL CRASH

The following table shows the activities for a project.
TIME (WEEKS) COST ($)
ACTIVITY IMMEDIATE
PREDECESSOR(S
)
NORMAL CRASH NORMAL CRASH AVAILABL
E WEEKS
OF
CRASHING
CRASHIN
G COST /
WEEK
A Start 323,0003,300
B Start 648,0009,000
C A 114,0004,000
D A 543,5004,000
E B 434,7505,500
F C 222,0002,000
G D 114,0004,000
H D,F 323,5003,750
I E,G 323,0004,250
J E 215,0007,000
Finish H, I, J --------
a. Draw the network diagram.
b. What is the critical path for the project using the normal time?
c. Complete the table by filling the missing information.
d. How many week(s) of crashing are available for activity E?
e. Which activity should be crashed first?
6.(12 pts) A professor records the number of complaints from his students each semester
throughout a 15-semester period. The sample size for each sample is 50 students, what are 3-
sigma control limits for this class? Construct a control chart and interpret the data.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!