Question: QUESTION 2 ( 1 0 MARKS ) Mario Manufacturing Sdn . Bhd . develops a new pollution control device for treating waste water from steel

QUESTION 2(10 MARKS)
Mario Manufacturing Sdn. Bhd. develops a new pollution control device for treating waste water from steel industries. The development and installation of this device requires nine (9) activities and their related time estimates and costs are given in Table 2.
Table 2: Activities, time estimates and costs for pollution control device installation
\table[[Activity,\table[[Immediate],[Predecessor(s)]],\table[[Normal time],[(weeks)]],\table[[Maximum Crash],[time (weeks)]],\table[[Crash cost],[per week],[(RM)]]],[A,-,9,1,1900],[B,A,7,3,2100],[C,A,3,1,2500],[D,B,6,3,2700],[E,B,8,1,1400],[F,C,4,2,5000],[G,E, F,6,2,1600],[H,D,5,2,1000],[I,H,3,1,2300]]
a. Construct a network diagram based on Activity-on-Node (AoN) for the above development project. Determine the minimum project completion time and the critical path activities.
(4 marks)
b. If the completion time of the project needs to be shortened by two (2) weeks, determine which activities are involved to provide minimum additional cost. Show the final network diagram after these changes.
(6 marks)
 QUESTION 2(10 MARKS) Mario Manufacturing Sdn. Bhd. develops a new pollution

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!