Question: Question 2 ( 1 0 marks ) : The information of a project network is shown below. begin { tabular } { | c

Question 2(10 marks):
The information of a project network is shown below.
\begin{tabular}{|c|c|c|c|c|}
\hline Activity & \begin{tabular}{c}
Precedence \\
Activities
\end{tabular} & \begin{tabular}{c}
Optimistic \\
Time \\
(rapks)
\end{tabular} & \begin{tabular}{c}
Most Probable \\
Time \\
(wacks)
\end{tabular} & \begin{tabular}{c}
Pessimistic \\
Time \\
(ragcks)
\end{tabular}\\
\hline A & -- & 3 & 4 & 5\\
\hline B & - & 3 & 3.5 & 7\\
\hline C & B & 4 & 5 & 6\\
\hline D & A, C & 2 & 3 & 4\\
\hline E & B & 6 & 10 & 14\\
\hline F & B & 7.5 & 8.5 & 12.5\\
\hline G & E & 4.5 & 6 & 7.5\\
\hline H & E & 5 & 6 & 13\\
\hline I & D, G & 2 & 2.5 & 6\\
\hline J & F, H & 4 & 5 & 6\\
\hline
\end{tabular}
Determine the amount of slack associated with each activity using a forward and a backward pass method by completing the following table.
\begin{tabular}{|c|c|c|c|c|c|c|c|c|}
\hline \begin{tabular}{c}
Activit \\
y
\end{tabular} & \begin{tabular}{c}
Precedence \\
Activities
\end{tabular} & \begin{tabular}{c}
Expected \\
Time \\
(weeks)
\end{tabular} & \( E S \) & \( L S \) & \( E F \) & \( L F \) & Slack & Path? \\
\hline A & - & & & & & & & \\
\hline B & - & & & & & & & \\
\hline C & B & & & & & & & \\
\hline D & A, C & & & & & & & \\
\hline E & B & & & & & & & \\
\hline F & B & & & & & & & \\
\hline G & E & & & & & & & \\
\hline H & E & & & & & & & \\
\hline I & D, G & & & & & & & \\
\hline J & F, H & & & & & & & \\
\hline
\end{tabular}
Question 2 ( 1 0 marks ) : The information of a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!