Question: QUESTION 4 a ) . Given the following information for a project, draw the AON ( Activity - On - Node ) project network. (

QUESTION 4
a). Given the following information for a project, draw the AON (Activity-On-Node) project network. (10 marks)
Activity
Immediate Processor
Activity Time (days)
A
-
6
B
-
8
C
A, B
5
D
B
4
E
C
7
F
C, D
3
G
D
6
H
E, F, G
5
b). Figure to accompany Table 4
Table 4
Activity
Activity Time
Earliest Start
Earliest Finish
Latest Start
Latest Finish
Slack
A
2
0
0
2
0
B
1
2
3
3
4
1
C
3
2
5
2
5
0
D
7
3
10
4
11
E
3
5
8
11
3
F
5
11
5
11
0
G
4
11
15
11
15
0
Using the information shown in Table 4, what is the slack time for activity D?(2 marks)
Using the information shown in Table 4, what is the earliest finish time for activity A?(2 marks)
Using the information shown in Table 4, what is the latest start time for activity E?(2 marks)
Using the information shown in Table 4, what is the activity time for activity F?(2 marks)
Refer to the Figure to accompany Table 4. Which one of the following is the critical path? (2 marks)
Using the information shown in Table 4, what is the project duration? (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!