Question: QUESTION 4 a ) . Given the following information for a project, draw the AON ( Activity - On - Node ) project network. (
QUESTION
a Given the following information for a project, draw the AON ActivityOnNode project network. marks
Activity
Immediate Processor
Activity Time days
A
B
C
A B
D
B
E
C
F
C D
G
D
H
E F G
b Figure to accompany Table
Table
Activity
Activity Time
Earliest Start
Earliest Finish
Latest Start
Latest Finish
Slack
A
B
C
D
E
F
G
Using the information shown in Table what is the slack time for activity D marks
Using the information shown in Table what is the earliest finish time for activity A marks
Using the information shown in Table what is the latest start time for activity E marks
Using the information shown in Table what is the activity time for activity F marks
Refer to the Figure to accompany Table Which one of the following is the critical path? marks
Using the information shown in Table what is the project duration? marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock