Question: Question 2 1 ( 1 point ) Angela is the new project manager in the company and needs to submit the WBS for the project
Question point
Angela is the new project manager in the company and needs to submit the WBS for the project within a day. She is looking for some help. Since you have been with the company for quite a sometime, you help her by providing a scope statement from a previously completed similar project. She is happy to see that as she can use a lot of data from that document to begin with.
This type of approach for creating the WBS is called:
Bottomup approach
Topdown approach
Analogous approach
Best practice sharing approach