Question: QUESTION 2 [ 1 5 MARKS ] Consider the following work breakdown structure ( WBS ) compiled for Transport project ABC for period 1 .

QUESTION 2
[15 MARKS]
Consider the following work breakdown structure (WBS) compiled for Transport project ABC for period 1. The WBS for period 2 requires revision and several updates are to be effected. Answer only the questions considering the WBS given for Transport project ABC incorporating the updates for period 2.
Revised updates to be considered for the WBS for Transport project ABC for period 2(1 November 2023-31 March 2024):
a) Due to conditions, the cost for general labour resources is revised because less general labour is needed, and therefore a cut of 5% in this costing item is required.
b) A fire resulted in the project facilities no longer being available - a new facility has been identified but at a higher monthly rate than the previous building. An increase of 12.5% needs to be incorporated.
c) Due to economic conditions and the financial pressures on the stakeholders, the professional project staff accepted a 4% cut in their fee structure.
d) The technical resources needed are far less than anticipated, bringing about an overall cut on this cost item of 15%.
e) New specifications on transportation required demand an increase of 6% on this cost item.
f) Due to maintenance problems at Eskom and continuous increases in energy rates, the energy resources item is revised with an increase of 18%.
g) Excellent new software is now available, which can enhance the quality of work done on the project - it has a cost implication of an additional 7.5%.
h) Fendi noted that due to a liquidation sale, his team was able to obtain materials at a much lower price than anticipated - this brings about a 20% cut in the costing of materials resources.
i) Due to damage, hardware support needs additional funding to make new computers available to technicians working on the project - this results in a 10% increase of this costing item.
 QUESTION 2 [15 MARKS] Consider the following work breakdown structure (WBS)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!