Question: Question 2 ( 1 5 % ) : The operations manager of Green Apple Juice Co . is concerned about the quality of the company

Question 2(15%):
The operations manager of Green Apple Juice Co. is concerned about the quality of the companys 8-oz
bottle filling line and will track it. The bottles need to be filled according to the specified tolerances for this
product because the nutritional details on the label indicate that the serving size is 8 ounces. The product's
design standard specifies a fill level of 8.00 ounces, with a tolerance of \pm 0.067 ounces. The manager
gathered nine observations and obtained the next samples data during the production process:
Sample
Fluid oz per bottle
Average Range
18.030.09
27.990.13
37.980.09
48.030.10
58.030.13
68.010.09
78.020.06
88.000.06
97.990.05
107.990.11
a. Calculate all the - chart and R-chart limits for this process. Is the process in control? Explain.
b. The results for new three samples of 8-oz bottle juice filling are:
Page 11 of 12
Sample
Observation
123456789
17.987.937.938.027.957.967.957.988.00
27.977.968.048.028.017.978.058.047.99
37.957.967.907.958.008.027.967.978.01
Is the process in control? Explain.
c. Calculate the process capability ratio and the process capability index. Is the process capable of meeting
the design standard? Explain.
d. What percentage of 8-oz bottle filling will lie within the control limits obtained in part a, given the mean
products design standard (process distribution)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!