Question: Question 2 ( 1 point ) An activity has an early start of 5 and its late start is 8 . This activity has days

Question 2(1 point)
An activity has an early start of 5 and its late start is 8. This activity has days of total slack.
1
2
3
4
5
Question 3(1 point)
The cost injpact of a risk event occurring as a project proceeds through its life cycle
 Question 2(1 point) An activity has an early start of 5