Question: 7. (1 point) An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of

7. (1 point) An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. What is the activity's slack? (select the best answer) a 3 b. 6 C. 10 d. 19 8. (1 point) In critical path analysis, a activity (select the best answer) determines the early start and early finish dates for each a. backward pass b. late start date c. forward pass d. late finish date