Question: 7. (1 point) An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of

7. (1 point) An activity has an early start (ES)

7. (1 point) An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. What is the activity's slack? (select the best answer) a 3 b. 6 C. 10 d. 19 8. (1 point) In critical path analysis, a activity (select the best answer) determines the early start and early finish dates for each a. backward pass b. late start date c. forward pass d. late finish date