Question: Question 2 ( 1 point ) Listen Below is the information on a small project. All information is in days and the crash time is

Question 2(1 point)
Listen
Below is the information on a small project. All information is in days and the crash time is the amount of time that the project can be shortened along with the associated cost of crashing.
\table[[Activity,\table[[Time],[In Days]],\table[[Immediate],[Predecessor(s)]],\table[[Crash Time],[(Days)]],Crash Cost],[P,9,none,1,$400/Day],[L,5,P,2,$100? Day],[I,8,P,1,$150? Day],[N,9,L,I,1,$200? Day],[K,4,N,I,2,$500? Day]]
Hint: In order to be successful in this activity you must draw out the AON diagram on your own in order best answer the following questions.
What is the expected project length?
21 days
28 days
30 days
None of these are correct
27 days
 Question 2(1 point) Listen Below is the information on a small

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!