A project consists of seven activities. The following table shows the estimated time of the activities and the precedence relations.
\table[[Activity,\table[[Estimated],[durations (days)]],\table[[Immediate],[predecessor]]],[A,9,],[B,10,A],[C,5,A],[D,3,B, C],[E,6,B, C],[F,3,D, E],[G,4,]]
What is the earliest project completion time?