Question: Question 2 (1 point) Saved A work activity is bursting into the next two following work activities. What action should the Project Manager NOT undertake

Question 2 (1 point) Saved A work activity is

Question 2 (1 point) Saved A work activity is bursting into the next two following work activities. What action should the Project Manager NOT undertake at the burst point? Ensure all preceding work activities have been successfully completed Check that both work activities use different resources and can be done concurrently Schedule the two work activities sequentially Perform Earned value analysis to determine current schedule performance