Question: QUESTION 2 1 Using the information in the table, the latest start ( LS ) time for activity G is a . 3 5 weeks

QUESTION 21
Using the information in the table, the latest start (LS) time for activity G is
a.35 weeks
b.29 weeks
c.26 weeks
d.31 weeks
q,
QUESTION 22
Using the information in the table, the critical path for this project consists of activities
a. A-B-C-D-E-F-G
b. A-D-F-G
c.B-C-E-G
d. B-D-F-G
 QUESTION 21 Using the information in the table, the latest start