Question: QUESTION 74 Using the above table, the latest start (LS) time for activity G is a. 31 weeks b. None of these alternatives is correct.

QUESTION 74 Using the above table, the latest
QUESTION 74 Using the above table, the latest
QUESTION 74 Using the above table, the latest start (LS) time for activity G is a. 31 weeks b. None of these alternatives is correct. c. 29 weeks d. 35 weeks e. 26 weeks USE THIS SCENARIO FOR THE NEXT SIX QUESTIONS A project consists of the following activities: Activity Activity Predecessor Time (Weeks) A 8 B 12 4 D AB , 10 7 E F D 9 G EF 8