Question: Question 2 10 pts Examine the project activity network below. 7 3 10 What would happen to the critical path and the project duration
Question 2 10 pts Examine the project activity network below. 7 3 10 What would happen to the critical path and the project duration of Activity F is delayed by two weeks? O The critical path would change and projection duration would become 23 weeks. O The critical path would stay the same but project duration would become 21 weeks. The critical path and projection duration would stay the same. O The critical path would change but project duration would stay the same... O The critical path would stay the same but project duration would become 23 weeks.
Step by Step Solution
There are 3 Steps involved in it
The detailed answer for the above question is provided below The image youve provided is of a projec... View full answer