Question: Consider the following table. Activity Duration Depends on A 2 days B 10 days A 2 days A D 2 days E 3 days C

 Consider the following table. Activity Duration Depends on A 2 days

Consider the following table. Activity Duration Depends on A 2 days B 10 days A 2 days A D 2 days E 3 days C F 2 days G 4 days B,D,E,F SA = system analyst; SD = system designer; SC = system coder Resource Type SA SD SD SC SC SC SA a. (10 pts) Draw up an activity network for the activities above, and identify the critical path (PERT). b. (10 pts) Draw up a resource table showing the number of each type of resource needed on each day of the project. c. (10 pts) Generate resource histogram for both SA and SC

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!