Question: QUESTION 2 ( 2 0 Marks ) 2 . 1 Using the data in the table below answer the questions that follow: Activity Predecassor Estimate

QUESTION 2(20 Marks)
2.1 Using the data in the table below answer the questions that follow:
Activity Predecassor Estimate in months Start -0 D Start 4 A Start 6 F D,A 7 E D 8 G F,E 5 B F 5 H G 7 C H 8 End C,B 0
2.1.1 Determine the minimum time in which the above project can be complete?
(5 marks)
2.1.2 Complete a forward and backward pass for the above table.
(10 marks)
2.1.3 To shorten the length of the project, the sponsor has offered to remove the work of activity E from the project, making D the predecessor to activities G and F. Redraw the AON diagram and explain the effect of the removed work activity on the critical path. (5 marks) DRAW DIAGRAM AND EXPLAIN ANSWERS, CLEAR DIAGRAM TO BE PLOTTED PLEASE
QUESTION 2 ( 2 0 Marks ) 2 . 1 Using the data in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!