Question: QUESTION 2 ( 2 0 Marks ) 2 . 1 Using the data in the table below answer the questions that follow: Activity Predecassor Estimate
QUESTION Marks
Using the data in the table below answer the questions that follow:
Activity Predecassor Estimate in months Start D Start A Start F DA E D G FE B F H G C H End CB
Determine the minimum time in which the above project can be complete?
marks
Complete a forward and backward pass for the above table.
marks
To shorten the length of the project, the sponsor has offered to remove the work of activity E from the project, making D the predecessor to activities G and F Redraw the AON diagram and explain the effect of the removed work activity on the critical path. marks DRAW DIAGRAM AND EXPLAIN ANSWERS, CLEAR DIAGRAM TO BE PLOTTED PLEASE
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
