Data provided in Table indicated succeeding and preceding information of activities on your project.
Table
tableActivityPredecessor,Duration MonthsABACADB CEDFDGE F
the data in the Table :
Develop a Network Diagram for your project
Determine the total floats or slacks for all activities
Identify the Critical Paths
Calculate the Project float if your client expects the project to be complete in months.
Explain your result