 QUESTION 2 [20 Marks ata provided in Table 2. 1 indicated

QUESTION 2 [20 Marks ata provided in Table 2. 1 indicated succeeding and preceding information of activities on oject. Table 2. 1 Activity Predecessor Duration (Months) A 5 B A C A D B, C 9 E D F D G E, F he data in the Table 2. 1: Develop a Network Diagram for your project Determine the total floats or slacks for all activities Identify the Critical Path(s) Calculate the Project float if your client expects the project to be complete in 40 mo Explain your result