Question: QUESTION 2 ( 2 0 marks ) With reference to the table below, determine the activities that are on the critical path and the expected
QUESTION marks
With reference to the table below, determine the activities that are on the critical path and the expected
time in which the project will be completed.
Activity Preceding
Optimisti
cTime Probable Time Pessimistic Time
A
B A
C A
D A
E B
F B
G C F
H D
I H
J G I
K E J
QUESTION marks
Discuss the factors that could lead to the successful implementation of Project Ingede, which focuses on
expanding Unilever South Africa's soup factory situated south of Durban.
QUESTION marks
In the context of capital projects, elaborate on the reasons why project managers are placing greater
emphasis on investing in risk management.
QUESTION marks
Using any relevant examples of your choice, examine the concept of "inaccurate project planning."
Discuss what this term encompasses and review the factors that can contribute to this.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock