Question: With reference to the table above, determine the activities that are on the critical path and the expected time in which the project will be

With reference to the table above, determine the activities that are on the critical path and the expected time in which the project will be completed.
\begin{tabular}{|c|c|c|c|c|} \hline Activity & Preceding & \begin{tabular}{c} Optimisti \\ cTime \end{tabular} & Probable Time & Pessimistic Time \\ \hline A & -- & 7 & 10 & 19 \\ \hline B & A & 2 & 2 & 8 \\ \hline C & A & 8 & 12 & 16 \\ \hline D & A & 3 & 5 & 10 \\ \hline E & B & 4 & 6 & 8 \\ \hline F & B & 6 & 8 & 10 \\ \hline G & C, F & 2 & 3 & 8 \\ \hline H & D & 2 & 2 & 16 \\ \hline I & H & 6 & 8 & 14 \\ \hline J & G, I & 4 & 6 & 8 \\ \hline K & E, J & 2 & 5 & 8 \\ \hline \end{tabular}