Question: Question 2 2 0 pts Tiles ( 1 2 1 2 ) can be installed at a rate of 4 5 per worker

Question 2
20 pts
Tiles (12"12") can be installed at a rate of 45 per worker hour. The floor of a large lobby area (100' by 50') is to be covered with these tiles. If five workers are assigned to this task, what duration (to the nearest whole day) should be assigned this activity? Assume 8 hour days