Question: Question 2 : [ 2 0 ] You're managing a project to set up an automated sorting system for a parcel distribution centre. Each activity

Question 2:
[20]
You're managing a project to set up an automated sorting system for a parcel distribution centre. Each activity represents a major task in the project, and the times given are estimates of how long each task will take.
\begin{tabular}{|l|l|l|l|}
\hline Activity & Description & \begin{tabular}{l}
Time Estimate \\
(days)
\end{tabular} & \begin{tabular}{l}
Immediate \\
Predecessors
\end{tabular}\\
\hline A & Initial Planning & 5 & -\\
\hline B & Site Preparation & 4 & -\\
\hline C & Equipment Procurement & 6 & A \\
\hline D & Layout Design & 3 & B \\
\hline E & Power and Network Setup & 6 & B \\
\hline F & Installation of Software & 2 & D \\
\hline G & Equipment Assembly & 5 & E \\
\hline H & Testing & 8 & C \\
\hline I & Final Integration and System Testing & 5 & F, G \\
\hline
\end{tabular}
2.1. Construct a network diagram for this process.
2.2. Determine ES, EF, LS, LF and slack for each activity.
2.3. Determine the critical path and project completion time.
(5)
 Question 2: [20] You're managing a project to set up an

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!