Question: Question 2 : [ 2 0 ] You're managing a project to set up an automated sorting system for a parcel distribution centre. Each activity

Question 2:
[20]
You're managing a project to set up an automated sorting system for a parcel distribution centre. Each activity represents a major task in the project, and the times given are estimates of how long each task will take.
\table[[Activity,Description,\table[[Time Estimate],[(days)]],\table[[Immediate],[Predecessors]]],[A,Initial Planning,5,-],[B,Site Preparation,4,-],[C,Equipment Procurement,6,A],[D,Layout Design,3,B],[E,Power and Network Setup,6,B],[F,Installation of Software,2,D],[G,Equipment Assembly,5,E],[H,Testing,8,C],[I,Final Integration and System Testing,5,F, G]]
2.1. Construct a network diagram for this process.
2.2. Determine ES, EF, LS, LF and slack for each activity.
(11)
2.3. Determine the critical path and project completion time.
 Question 2: [20] You're managing a project to set up an

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!