Question: QUESTION 2 2 . 1 As an industrial engineering employee of an organisation, discuss the appropriateness of calculating cost performance index ( CPI ) and

QUESTION 2
2.1 As an industrial engineering employee of an organisation, discuss the
appropriateness of calculating cost performance index (CPI) and write down its
formula. (3 marks)
2.2 If Planned value (PV) is simply R13500. In order to calculate the planned value
(PV) we need to multiply the earned value (EV) by the percentage of the project that
is complete of 65%. If the actual cost (AC) is R9600, how would you determine the
following?
a) The earned value (EV)(3 marks)
b) The cost variance of that month. (3 marks)
c) Cost performance index (3 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!