Question: Question 2 ( 2 + 2 + 2 + 2 = 8 points ) We have a process as shown in the right figure. (

Question 2(2+2+2+2=8 points)
We have a process as shown in the right figure. (M1-M4 are the names for four machines. The numbers are activity times in minutes). Consider the following schedule:
Schedule a job on M1 every 10 minutes, starting at time 0; schedule a job on M2 every 5 minutes starting at time 0. Jobs finished on M1 go to M3; jobs finished on M2 go to M4.
The Gantt chart for the first 6 jobs is below:
12345678910111213141516171819202122232425262728
M1111111444444
M222335566
M311111111114444444444
M42222333355556666
You can extend the above chart as needed.
Machine WIP (units)
M1
M2
M3
M4
Total
a) Find the WIP on each machine and complete the below table.
b) What is the average throughput time, i.e., flow time [in mins]?
(Hint: Every 10 minutes, 3 jobs come to the process (1 job to M1,2 jobs to M2). To get the average throughput time (TPT), you need to calculate the TPT for each of the three jobs and then take the average. Do not round your answer. )
c) Is the process demand- or supply-constrained? What is the flow rate under the given schedule (in units/hour)?
d) What is the actual cycle time under this schedule (in minutes)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!