Question: QUESTION 2 . 2 Description: You are a project manager overseeing the design and programming of a new software system to replace the old manual
QUESTION
Description:
You are a project manager overseeing the design and programming of a new software
system to replace the old manual material requirements suite that was used by the
programme office. Note: see yourself as an IT project manager
The activity table below was compiled with the entire team and the customer is awaiting
the final schedule and costs to prepare for the budgetary provision of the entire project.
You are the project manager PM Peter is the System Software Specialist and reports
to you. He also supervised the User Requirement Specifications and confirmed the
budget.
Fani is the Application Software specialist and also reports to you. He knows all the
licensing requirements and the programming staff report to him. Annie is in charge of
the licensed programming team and Jan is responsible for the client development team.
Both Annie and Jan report to Fani.
Andrew is the AGILE PM expert that does team building and team scrums Andrew
reports directly to you as the PM
Sifiso is in charge of the development server where all the programming integration is
thoroughly tested before commissioning. Sifiso reports to Peter, who also oversees the
quality control.
Study the Activity Table below and execute the following:
Activity Table
ID DESCRIPTION PREDECESSOR Resources TIME# COSTS RESPONSIBLE
A Receive Scope & Budget NONE RYou
B URS Received & signed off A RYou
C System Software Spec. B R Peter reports to PM
D Application SW Planning B R Fani reports to PM
E SW License Design & Plan CD complete Annie reports to Fani
F Application SW Design CD complete Jan reports to Fani
G MRP Gap Analysis SPRINT EF complete Andrew reports to PM
H Customisation of Apps SW G complete Fani reports to PM
I Client Programming Teams G complete Jan reports to Fani
J Test Server Module Tests H I complete Sifiso reports to Peter
K Quality Management J complete Peter reports to PM
L Handover & Training K complete Annie reports to Fani
TOTAL
# Time in WEEKS
Consider all resources employed at Rweek
Complete the COSTS column in the table below and add the TOTAL.
YOU are the project manager and not all are reporting directly to you, draw a simple OBS
organisational breakdown structure also called the Project Organigram.
Draw a project network that includes all the activities.
Show the critical path
Calculate the total slack SHOW the total Slack
Draw a master schedule use costs, early start figures
Upload resources and develop a resource histogram.
Develop an Scurve based on the information. NOTE: Use the COST column for the Scurve
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock