Question: QUESTION 2 . 2 Description: You are a project manager overseeing the design and programming of a new software system to replace the old manual

QUESTION 2.2
Description:
You are a project manager overseeing the design and programming of a new software
system to replace the old manual material requirements suite that was used by the
programme office. (Note: see yourself as an IT project manager)
The activity table below was compiled with the entire team and the customer is awaiting
the final schedule and costs to prepare for the budgetary provision of the entire project.
You are the project manager (PM). Peter is the System Software Specialist and reports
to you. He also supervised the User Requirement Specifications and confirmed the
budget.
Fani is the Application Software specialist and also reports to you. He knows all the
licensing requirements and the programming staff report to him. Annie is in charge of
the licensed programming team and Jan is responsible for the client development team.
Both Annie and Jan report to Fani.
Andrew is the AGILE PM expert that does team building and team scrums. Andrew
reports directly to you as the PM.
Sifiso is in charge of the development server where all the programming integration is
thoroughly tested before commissioning. Sifiso reports to Peter, who also oversees the
quality control.
Study the Activity Table below and execute the following:
Activity Table
ID DESCRIPTION PREDECESSOR Resources TIME# COSTS RESPONSIBLE
A Receive Scope & Budget NONE 11 R25,000(You)
B URS Received & signed off A 11 R25,000(You)
C System Software Spec. B 13 R75,000 Peter (reports to PM)
D Application S/W Planning B 34 R300,000 Fani (reports to PM)
E S/W License Design & Plan C,D 34(complete) Annie (reports to Fani)
F Application S/W Design C,D 35(complete) Jan (reports to Fani)
G MRP Gap Analysis (SPRINT) E,F 34(complete) Andrew (reports to PM)
H Customisation of Apps S/W G 43(complete) Fani (reports to PM)
I Client - Programming Teams G 97(complete) Jan (reports to Fani)
J Test Server Module Tests H, I 1012(complete) Sifiso (reports to Peter)
K Quality Management J 52(complete) Peter (reports to PM)
L Hand-over & Training K 32(complete) Annie (reports to Fani)
TOTAL
# Time in WEEKS
(Consider all resources employed at R25,000/week)
1. Complete the COSTS column in the table below and add the TOTAL.
2. YOU are the project manager and not all are reporting directly to you, draw a simple OBS
(organisational breakdown structure) also called the Project Organigram.
3. Draw a project network that includes all the activities.
4. Show the critical path
5. Calculate the total slack (SHOW the total Slack)
6. Draw a master schedule (use costs, early start figures)
7. Upload resources and develop a resource histogram.
8. Develop an S-curve based on the information. (NOTE: Use the COST column for the S-curve)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!